Entwurf • Design Burkard Meyer Architekten, CH-Baden
                                                                          Bauherr • Client Erne AG Holzbau, CH-Laufenburg
                                                                          Standort • Location CH-Stein
                                                                          Nutzfläche • Floor space 2483 m 2
                                                                          Fotos • Photos Roger Frei, CH-Zürich
                                                                          Mehr Infos auf Seite • More infos on page 142



             Längsschnitt • Longitudinal section









































             Grundriss Erdgeschoss • Ground floor plan                    Grundriss 1. Obergeschoss • Floor plan level +1




             Meyer office regrets. “For the timber-construction company, clay is above all a labour
             of love that continues.” But of course, the unplastered clay characterizes the rooms and
             also regulates the indoor climate. The extension represents a sustainable model for the
             next generation of office buildings, combining the concept of material cycle, minimal use
             of raw materials, smart material combinations and natural materials under one roof.

             Sustainable and forward­looking – and demountable

             Representative of current strategies for CO2-reduced construction, the new building fol-
             lows the Design for Disassembly concept – even in its external appearance. The filigree
             façade structure made of aluminium and glass is complemented on both sides by hori-
             zontally arranged photovoltaic elements, which, together with the awnings, lend the
             building a certain lightness. The 638 square metres of photovoltaic modules produce
             78,000 kWh of ecological electricity per year. The half-timbered construction can be
             easily dismantled, sorted by type and rebuilt elsewhere if necessary. The combination of
             existing timber modular construction and newly added timber-hybrid construction has
             many advantages. In addition to the varying amount of space that is now available, the
             complex also features two complementary forms of prefabrication, reflecting the diffe-
             rent areas of expertise of the building owners. Close cooperation between the building
             owners and the planners during the construction of the building resulted in a building
             that is exemplary in terms of construction and operation, and which also translates
             an industrial planning- and manufacturing logic into a harmonious spatial experience.  Grundriss 2. Obergeschoss • Floor plan level +2